Project: SUNRAIL – Phase 2 South Track & Stations
Location: Kissimmee, Florida
Client: Dana b. Kenyon Company (Station/VSLMF Building subcontractor for Middlesex-Herzog J/V)
Service: Scheduling & Project Controls Consultant
Role: Lead Schedule & Project Controls Consultant
Delivery: Subcontract
Main Contract Value: $113,700,000+
Duration: 2016 to 2018
Description: Southern Expansion linking Sand Lake Road in Orange County to Poinciana in Osceola County. This is a 17.2-mile segment that will feature four new stations at Meadow Woods in Orange County, and the Tupperware Station, downtown Kissimmee Station and the Poinciana Station in Osceola County. Plans also include double tracking most of the corridor, improving grade crossings and building the four new stations and platforms, expected to be up and running by mid 2018.